Evidence

Yn dangos sylwadau a ffurflenni 1 i 7 o 7

Gwrthwynebu

Publication Draft

ID sylw: 64520

Derbyniwyd: 26/05/2014

Ymatebydd: Mr Richard Thwaites

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Ydi

Crynodeb o'r Gynrychiolaeth:

The evidence used to select the preferred option for development was factually inaccurate leading to a flawed decision.

Cefnogi

Publication Draft

ID sylw: 65133

Derbyniwyd: 24/06/2014

Ymatebydd: Sport England

Crynodeb o'r Gynrychiolaeth:

Paragraph 1.38

As a point of clarification, the Sports Pitches and indoor sports strategy are not completed, if they are not completed and adopted by the time of the EIP, I would have to consider them unsound as an evidence base.

Gwrthwynebu

Publication Draft

ID sylw: 65319

Derbyniwyd: 25/06/2014

Ymatebydd: Mr Brian Bate

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Nac Ydi

Crynodeb o'r Gynrychiolaeth:

Re: Strategic Transport Assessment.

The Assessment did not include the fact that there is a river and a railway running through Warwick and Leamington Spa. The only road into Warwick has a river bridge. The assessment shows improvements to a junction just prior to the bridge but does not consider that improving the junction cannot change the number of vehicles using the bridge.

The Assessment also did not include vehicle movements going to and from Schools. These journeys add considerably to the morning traffic figures.

Gwrthwynebu

Publication Draft

ID sylw: 65327

Derbyniwyd: 25/06/2014

Ymatebydd: Mr Carl Stevens

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Ydi

Crynodeb o'r Gynrychiolaeth:

Evidence has not been assessed fully enough at a local level to each recommended site in the plan

Gwrthwynebu

Publication Draft

ID sylw: 65362

Derbyniwyd: 27/06/2014

Ymatebydd: Cycleways

Asiant : Cycleways

Cydymffurfio â’r gyfraith? Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Ydi

Crynodeb o'r Gynrychiolaeth:

This objection relates to the STA evidence document.
With regard to cycling, as part of the SWOT analysis (table 2.1, p.16), it quotes a "well developed cycling network" as presented as a strength of the area. In section 2.2.24 the document refers to a figure of 3.5% of the population as cycling to work from the 2001 census while also claiming that the "cycle network has been expanded and improved over the last 10-15 years" (section 2.2.22). However, more recent census data from 2011 (http://www.ons.gov.uk/ons/rel/census/2011-census-analysis/cycling-to-work/2011-census-analysis---cycling-to-work.html ) show a decline in the cycling to work percentage from the 3.5% in 2001 to 3.1% for the district.
Thus, in spite of the investment in cycle infrastructure over the last 10 years there has been no corresponding increase in cycling. The 2011 census also shows that in the same timeframe other local authorities have succeeded in increasing these percentages from similar levels over the last 10 years to much higher percentages in 2011. The lack of an increase in cycling in the Warwick District, in spite of the increase in the cycling infrastructure, could be attributed to its poor quality, as identified in a recent study by Cycleways, (http://www.cycleways.org.uk/campaign/review-of-cycling-provision/).
The study shows that much of the problem lies in poor design and in non compliance of planning standards. In addition, one of the most salient features of the STA, in relation to cycling, is the lack of an integrated approach to transport, as identified in Cycleways' Cycle Review (section 7.1.2.).
In conclusion, there is no evidence base to support the claim of a well developed cycling network that encourages more sustainable transport in the district and would be able to mitigate increases in transport from the proposed developments of the Local Plan. Getting the evidence wrong has resulted in a lack of development planning for sustainable transport options and cycling in particular in the Local Plan.

Gwrthwynebu

Publication Draft

ID sylw: 65563

Derbyniwyd: 27/06/2014

Ymatebydd: Midland Red (South) Ltd. dba Stagecoach Midlands

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Nac Ydi

Crynodeb o'r Gynrychiolaeth:

The Plan has failed to evaluate a strategy that better mitigates transport impacts by focusing on sustainable transport measures, which may be more cost-effective and deliverable. The evidence base of the plan with regard to transport impacts has followed, not informed the preparation of the Plan. The LPA has failed to positively consult with Stagecoach to inform the Plan strategy

Atodiadau:

Gwrthwynebu

Publication Draft

ID sylw: 66022

Derbyniwyd: 27/06/2014

Ymatebydd: Centaur Homes

Asiant : McLoughlin Planning

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Nac Ydi

Crynodeb o'r Gynrychiolaeth:

Para 1.38 Centaur Homes object to the evidence used to formulate the plan. It is not considered fully up to date and therefore, not in accordance with paragraph 158 of the NPPF