Mod PM13 - Policies Map 13 Cubbington
ID sylw: 69463
Derbyniwyd: 21/04/2016
Ymatebydd: Cubbington Parish Council
Cydymffurfio â’r gyfraith? Heb nodi
Cadarn? Nac Ydi
Dyletswydd i gydweithredu? Heb nodi
The two fields now assigned the reference H50 were not identified as candidates during previous discussions, and no views have been exchanged between WDC and the PC who would not have agreed it a suitable location.
WDC assessment of H50
Village Profile and Housing Allocations document:
The PC agrees that, as identified in this assessment, there are three major constraints: surface water run-off and flood risk, landscape considerations, and encroaching into the Green Belt. These constraints are significant enough to render the decision to develop as unsound.
Surface water run-off and flood risk
Susceptibility to flooding -
A recent severe flood event has alerted residents to the risk of flooding in the low-lying parts of the old village core. At-risk streets have the potential to act as a basin for surface water run-off from the farmland on the hills that surround the village, particularly those to the north and east. Flooding has occurred despite the existence of the Pingle Brook Flood Alleviation Scheme; the volume of water involved in the flood event overwhelmed capacity.
A new flood alleviation scheme has been in operation since 2014. The scheme collects run-off from fields east of the village, stores it in a balancing pond and by-passes the village to discharge outside. Doubts remain about the adequacy of storm water drainage serveing the at-risk parts of the village.
The new flood alleviation scheme has proved to be a satisfactory solution to the Cubbington flooding problem. Changes to the hydrological characteristics of the village environment exceed the design limits of the scheme in future.
WDC evaluation of flood risk
WDC Level 1 Strategic Flood Risk Assessment (SFRA)
There are contradictions in the report which result in the
conclusion drawn in SA04 - that "unless local plan policies are developed to address the issues of flooding with regard to new development in Cubbington, given its sensitivity there are likely to be major short to long-term negative effects" - is based upon a false assumption.
This mistaken interpretation is carried forward into the February 2016 Sustainability Appraisal Addendum Report (SAAR), acknowledges that H50 "is located adjacent to an area of flood risk in the southern corner of the site, and is also susceptible to surface water flooding along the eastern border". Whilst the PC concurs with this assessment, it views it as an understatement of the contribution that the two fields make to surface water run-off. As the SAAR correctly reports, "surface water drains to the watercourse south of the site" and this ditch feeds the Pingle Brook.
Despite this broadly correct assessment, the SAAR concludes that "there is sufficient mitigation available to ensure that there will be a residual neutral effect against SA Objective 11".
In paragraph 7.6, the Village Profile and Housing Allocations report concedes that "Cubbington has a history of surface water flooding particularly surface water arising from the eastern side of the village". However, the same paragraph refers to "recent flood assessments [that suggest] that the area to the north of Rugby Road has low susceptibility to flooding as does much of the area to the south of Rugby Road". Despite this observation being counter to the earlier SFRA and also to the experience of Cubbington residents. There is no source for this risk downgrading provided. The contrary assessment is based upon the opinion of a drainage engineer who is a WDC officer.
The WDC officer's summary of the flood risk from development of the northern field is:
"The site will not cause increased flooding to south Cubbington village although surface water runoff should be carefully managed not to flood the village."
His/her opinion of the position regarding development of the southern field is:
"The site is likely to increase flooding onto the Cubbington village and surface water management plan should be implemented to control discharge to the Pingle Brook and reduce downstream flooding."
The PC views drainage and flood alleviation schemes a poor substitute for avoiding/creating/exacerbating sources of flood water. The PC is astounded that a recommendation made by an internationally-renowned firm of consultants has been cast aside by WDC on the say so of one of its officers.
It is the PC's view that the recommendation of the SAAR should only be rejected if a detailed hydrological survey, commissioned from an independent consultancy, shows that the SAAR recommendation is unwarranted.
Planning policy requirements
Policy FW1 in considering applications for development in areas that are at risk from flooding requires development to be "directed away from areas of flood risk", but does allow development to be considered in extremis, subject to certain criteria also being satisfied. One such criterion b) is that it must be demonstrated that "no suitable alternative sites are available in an area of lower risk": we can find no demonstration specific to H50 in the WDC documentation. A second criterion that is very relevant to H50 is d, which requires, inter alia, that the proposed development "does not increase the flood risk on site or elsewhere". The PC's view is that, even with SUDS, development on H50 will increase flood risk to parts of the old village core.
On at least two counts, any housing development on H50 carries the risk of contravening WDC's own policy. The PC accepts that any specific proposal for development on H50 will be judged against the requirements of Policy FW1, but feels that its inclusion in the LP makes a presumption for development.
The PC believes that the flood risks associated with development mean that these fields should be safeguarded from development under Policy FW1.
Further in the light of the opinion in the SFRA that "future development is avoided", a review should be carried out of the flooding risk associated with the inclusion of sites H25 and H26 in the LP.
Landscape impacts
WDC assessment of landscape value
Landscape Sensitivity and Ecological and Geological Study, Nov 2013. The northern field of H50 lays within parcel CB-03 and the southern field in CB-04. Both parcels have been rated as having "high" sensitivity to housing development, and assessed as "unsuitable for [housing] development".
In February 2015 document SA10 Sustainability Appraisal Report two sites within CB-03 (CU3*O Allotment Gardens Coventry Road and CU4*O Waverley Equestrian Centre) were rejected on the grounds that it "would lead to a significant finger of new development into an area of high landscape value"
In paragraph 7.5 of its February 2016 report Village Profile and Housing Allocations WDC acknowledges the November 2013 assessment, but qualifies it as having been "undertaken prior to HS2 being confirmed". WDC "has sought clarification on the impact that HS2 has on land parcels to the east of the village - notably parcel CB03 and CB04". This reassessment has resulted in H50 being regarded differently:
* The northern field "is still considered to be of high landscape sensitivity because any development here will be visually prominent as it would be on higher ground"
* The report appears to downplay the landscape impacts of housing development on the southern field, without seeking to rerate it from high.
The Parish Council treats this reassessment with suspicion. We do not regard the November 2013 assessment as being in any way compromised by HS2 because:
* HS2 will have little landscape impact as track/train will be in a cutting.
* Whilst there may be more significant landscape impacts when HS2 is under construction, the bulk of this work is likely to be completed before development of H50 as it will be necessary to complete the realignment of the B4453 required to accommodate HS2 before H50 work can commence.
* The November 2013 report refers to HS2 being a future feature in the landscape east of Cubbington, but make no comment that it would affect landscape rating
* WDC does not include HS2 as a reason for downgrading the landscape importance of the southern field.
The PC believes that the high landscape value attributed should stand.
Planning policy
Sub-paragraph f of Policy DS4 refers to areas assessed as having a high landscape value and promises that all such sites will be "avoided". No variation is envisaged by DS4. It therefore appears, prima facie, the inclusion of H50 is in breach of policy.
Green Belt
Significance of Green Belt
H50 lies wholly within the Green Belt parcel identified as CB1 in the June 2015 Joint Green Belt Study with a score of 13/20 assessed against the five purposes of Green Belt. Whilst this score rates CB1 as 'mid-performing', it is obvious that it restricts urban sprawl and rural encroachment. The PC regards H50 as a more substantial encroachment into the Green Belt around Cubbington than H25 or H26: it results in a significant closing of the gap with Weston under Wetherley.
Impact of HS2
In its February 2016 report Village Profile and Housing Allocations WDC acknowledges that the Green Belt parcel containing H50 "plays a role in safeguarding the countryside from encroachment" The report qualifies this, however, by pointing out that "the route of HS2 lays only one field beyond the site boundary" and that this fact "limits the weight that can be applied to the role this site plays in safeguarding countryside from encroachment".
The PC does not concur. Whilst it regards HS2 as an unwelcome encroachment it does not see it as a particularly significant one. Land loss is small, and linearly dispersed. The PC sees HS2 as a one-off loss of Green Belt and does not envisage that it will spawn associated development.
Planning policy
The PC feels that the policy of Green Belt has served the UK well but regards it as under increasing threat from developers. Despite this, it sees the Green Belt as equally, if not more, relevant than it has been at any time.
The PC recognises that, despite identifying the protection of the Green Belt as a function of one of the twelve core land-use planning principles set out in the NPPF, and claiming that "the Government attaches great importance to Green Belts", the same document also allows Green Belt boundaries to be altered through the preparation or review of the Local Plan". Sub-paragraph g of WDC policy DS4 promises that housing development within the Green Belt will be limited "to those locations where exceptional circumstances can be justified". Amongst these factors are whether alternative suitable sites exist outside the Green Belt, and whether the site within the Green Belt is able to meet "specific housing ... needs that cannot be met elsewhere". The PC has been unable to find any such specific justification for site H50.
Other matters
Improvement in infrastructure and village facilities.
It is admitted in the SAAR that "given the capacity of [H50] it is considered unlikely that development will deliver significant improvements to the local facilities and services on offer". The PC accepts this will mean that the new houses will place additional strain on the existing education and medical facilities used by Cubbington residents, without offering the prospect of some gains in services and facilities.
Any construction work in the southern field of H50 will have a direct detrimental impact on Cubbington CoE School which backs onto this field.
The H50 site is more than one kilometre from the Rugby Road shops.
Transport links
Within the works planned for HS2 the B4453 will be raised on an embankment. No mention has been made of this in WDC's analysis, nor of the potential effect this will have on the construction of access points from a housing development on H50.
The 538 bus route does not pass through Cubbington. There is a bus stop on Rugby Road, about four hundred metres from the H50 site. There is also one return 69 service per day along Rugby Road to Leamington Spa. Travelling by bus to Coventry currently requires changing services in Leamington.
The route of the 68 suffers significant traffic congestion. Proposals to extend some 68 services onward from Warwick to Coventry (service X68) from the summer of this year will exacerbate the current problems, as will the expected increase in traffic congestion south of Warwick and Leamington Spa that the LP proposals will engender. The X68 to Coventry is unlikely to attract travellers from Cubbington. Cubbington residents will prefer to change buses in Leamington, as now.
The most direct route to Coventry by car is via Coventry Road, negotiating a busy, high-speed junction at Coventry Road/Leicester Lane. All of the available routes are busy at peak times. There is no direct route to Coventry.
The PC therefore challenges the assessment in Table 3 in Village Profile and Housing Allocations that Cubbington has a "medium" relationship to Coventry. The PC regards links to Coventry as poor, and questions whether it should be identified as a site suitable for the additional housing required to accommodate Coventry's growth.