BASE HEADER
Proposed Modifications January 2016
Chwilio sylwadau
Canlyniadau chwilio Gladman Developments
Chwilio o’r newyddGwrthwynebu
Proposed Modifications January 2016
Mod 4 - Policy DS6
ID sylw: 68978
Derbyniwyd: 22/04/2016
Ymatebydd: Gladman Developments
Cydymffurfio â’r gyfraith? Ydi
Cadarn? Nac Ydi
Dyletswydd i gydweithredu? Heb nodi
Nuneaton and Bedworth are reluctant to take their share of the unmet need, this relates to the claimed constraints in the authority. Indeed in the Pre Submission version of the Nuneaton and Bedworth plan there was a shortfall of some 201 units per annum. There is therefore a concern about whether or not the housing needs of the HMA are being met in full.
The plan should also consider need from the Birmingham HMA where there is an unidentified need for 38,000 dwellings which may have knock on effects for Warwick
see attached
Gwrthwynebu
Proposed Modifications January 2016
Mod 5 - para 2.20
ID sylw: 69928
Derbyniwyd: 22/04/2016
Ymatebydd: Gladman Developments
Cydymffurfio â’r gyfraith? Nac Ydi
Cadarn? Nac Ydi
Dyletswydd i gydweithredu? Heb nodi
There is a need to allocate an additional layer of small to medium sites (circa 50-150 dwellings per site) to deliver additional housing in the first 5 years of the plan, to meet both the additional level of unmet HMA need and to provide a 5 year land supply. We believe that by identifying such sites, either through the allocation of omission sites or by giving consideration to the extension or enlargement of existing smaller allocations, it will be possible adopt a sound plan.
see attached
Gwrthwynebu
Proposed Modifications January 2016
Mod 6 - Policy DS7
ID sylw: 69929
Derbyniwyd: 22/04/2016
Ymatebydd: Gladman Developments
Cydymffurfio â’r gyfraith? Nac Ydi
Cadarn? Nac Ydi
Dyletswydd i gydweithredu? Heb nodi
There is a need to allocate an additional layer of small to medium sites (circa 50-150 dwellings per site) to deliver additional housing in the first 5 years of the plan, to meet both the additional level of unmet HMA need and to provide a 5 year land supply. We believe that by identifying such sites, either through the allocation of omission sites or by giving consideration to the extension or enlargement of existing smaller allocations, it will be possible adopt a sound plan.
see attached
Gwrthwynebu
Proposed Modifications January 2016
Mod 7 - paras 2.21 to 2.24
ID sylw: 69930
Derbyniwyd: 22/04/2016
Ymatebydd: Gladman Developments
Cydymffurfio â’r gyfraith? Nac Ydi
Cadarn? Nac Ydi
Dyletswydd i gydweithredu? Heb nodi
Picture on 5 year housing land supply, which the plan will provide upon adoption, is unclear.
Gladman acknowledge the trajectory produced alongside the
Proposed Modifications it is not made directly clear how this translates to a land supply position
From our initial calculations, and using the data as submitted in the Council's
trajectory, for the period 2016/17 to 2020/21 we calculate that only a 4.53 year land supply exists.
We are unsure the Council are claiming that the submitted plan will provide a 5 year housing land supply upon adoption
see attached
Gwrthwynebu
Proposed Modifications January 2016
Mod 17
ID sylw: 69931
Derbyniwyd: 22/04/2016
Ymatebydd: Gladman Developments
Cydymffurfio â’r gyfraith? Nac Ydi
Cadarn? Nac Ydi
Dyletswydd i gydweithredu? Nac Ydi
Gladman have concerns therefore that the Local Plan is not fully dealing with the issue of unmet need. In that context we
question the soundness of the current mechanism for plan review, which in theory could trigger an immediate review of the Local Plan. It would seem sensible to deal with these issues now.
see attached
Gwrthwynebu
Proposed Modifications January 2016
Mod 18 - paras 2.82 to 2.87
ID sylw: 69932
Derbyniwyd: 22/04/2016
Ymatebydd: Gladman Developments
Cydymffurfio â’r gyfraith? Nac Ydi
Cadarn? Nac Ydi
Dyletswydd i gydweithredu? Heb nodi
Gladman have concerns therefore that the Local Plan is not fully dealing with the issue of unmet need. In that context we
question the soundness of the current mechanism for plan review, which in theory could trigger an immediate review of the Local Plan. It would seem sensible to deal with these issues now.
see attached