BASE HEADER
Proposed Modifications January 2016
Chwilio sylwadau
Canlyniadau chwilio Environment Agency
Chwilio o’r newyddGwrthwynebu
Proposed Modifications January 2016
Mod 11 - paras 2.41 to 2.53
ID sylw: 68995
Derbyniwyd: 21/04/2016
Ymatebydd: Environment Agency
Cydymffurfio â’r gyfraith? Heb nodi
Cadarn? Heb nodi
Dyletswydd i gydweithredu? Heb nodi
Paragraph 2.41
We note that sites were assessed for their suitability against the SFRA Level 1. Warwick District Council's SFRA is dated April 2013 and we recommend that it is updated to take into account changes in Policy (NPPF) and the revised climate change allowances.
Warwick Local Plan
Proposed Modifications
Thank you for consulting the Environment Agency in relation to Proposed modifications to the Local Plan published in February 2016.
We have carefully reviewed the modifications proposed within the document based on the Planning Inspectors Interim Report and we find the it meets the tests of soundness:
We agree that the plan is positively prepared, justified, effective and consistent with national policy with the proposed modifications.
We have the following comments to make:
Modification 15
We support the wording of the proposed modification.
Modification 21 - Section 1.8
The Finham Brook, a designated Main River flows through the King's Hill site H43 near the southern boundary. We would support proposals to create land for open space and this should be linked in to the provision of green and blue infrastructure. Every opportunity should be taken to create additional flood storage to reduce the risk of flooding elsewhere.
Ammendments to Policy DS11 Paragraph 2.4.1
We note that sites were assessed for their suitability against the SFRA Level 1. Warwick District Council's SFRA is dated April 2013 and we recommend that it is updated to take into account changes in Policy (NPPF) and the revised climate change allowances. The Environment Agency updated their guidance on how climate change could affect flood risk to new developments - 'Flood risk assessments: climate change allowances' published on gov.uk on 19th February and came into immediate effect.
The update is based new scientific evidence. The main changes are to the peak river flow allowances. We are currently preparing new guidance which can be appended to the SFRA before the examination of the Local Plan is resumed.
Cefnogi
Proposed Modifications January 2016
Mod 15 - paras 2.66 to 2.68
ID sylw: 69050
Derbyniwyd: 21/04/2016
Ymatebydd: Environment Agency
We support the wording of the proposed modification.
See attached
Cefnogi
Proposed Modifications January 2016
Mod 21 - new paras New1.1 to New1.11
ID sylw: 69086
Derbyniwyd: 21/04/2016
Ymatebydd: Environment Agency
Section 1.8
The Finham Brook, a designated Main River flows through the King's Hill site H43 near the southern boundary. We would support proposals to create land for open space and this should be linked in to the provision of green and blue infrastructure. Every opportunity should be taken to create additional flood storage to reduce the risk of flooding elsewhere.
See attached
Cefnogi
Proposed Modifications January 2016
Mod 15 - paras 2.66 to 2.68
ID sylw: 69402
Derbyniwyd: 21/04/2016
Ymatebydd: Environment Agency
We have carefully reviewed the modifications proposed within the document based on the Planning Inspectors Interim Report and we find the it meets the tests of soundness:
We agree that the plan is positively prepared, justified, effective and consistent with national policy with the proposed modifications.
We have the following comments to make:
Modification 15
We support the wording of the proposed modification.
We have carefully reviewed the modifications proposed within the document based on the Planning Inspectors Interim Report and we find the it meets the tests of soundness:
We agree that the plan is positively prepared, justified, effective and consistent with national policy with the proposed modifications.
We have the following comments to make:
Modification 15
We support the wording of the proposed modification. Modification 21 - Section 1.8
The Finham Brook, a designated Main River flows through the King's Hill site H43 near the southern boundary. We would support proposals to create land for open space and this should be linked in to the provision of green and blue infrastructure. Every opportunity should be taken to create additional flood storage to reduce the risk of flooding elsewhere. Ammendments to Policy DS11 Paragraph 2.4.1
We note that sites were assessed for their suitability against the SFRA Level 1. Warwick District Council's SFRA is dated April 2013 and we recommend that it is updated to take into account changes in Policy (NPPF) and the revised climate
change allowances. The Environment Agency updated their guidance on how climate change could affect flood risk to new developments - 'Flood risk assessments: climate change allowances' published on gov.uk on 19th February and came into immediate effect.
The update is based new scientific evidence. The main changes are to the peak river flow allowances. We are currently preparing new guidance which can be appended to the SFRA before the examination of the Local Plan is resumed.
Cefnogi
Proposed Modifications January 2016
Mod 21 - new paras New1.1 to New1.11
ID sylw: 69403
Derbyniwyd: 21/04/2016
Ymatebydd: Environment Agency
We have carefully reviewed the modifications proposed within the document based on the Planning Inspectors Interim Report and we find the it meets the tests of soundness:
We agree that the plan is positively prepared, justified, effective and consistent with national policy with the proposed modifications.
We have the following comments to make:
Modification 21 - Section 1.8
The Finham Brook, a designated Main River flows through the King's Hill site H43 near the southern boundary. We would support proposals to create land for open space and this should be linked in to the provision of green and blue infrastructure. Every opportunity should be taken to create additional flood storage to reduce the risk of flooding elsewhere.
We have carefully reviewed the modifications proposed within the document based on the Planning Inspectors Interim Report and we find the it meets the tests of soundness:
We agree that the plan is positively prepared, justified, effective and consistent with national policy with the proposed modifications.
We have the following comments to make:
Modification 15
We support the wording of the proposed modification. Modification 21 - Section 1.8
The Finham Brook, a designated Main River flows through the King's Hill site H43 near the southern boundary. We would support proposals to create land for open space and this should be linked in to the provision of green and blue infrastructure. Every opportunity should be taken to create additional flood storage to reduce the risk of flooding elsewhere. Ammendments to Policy DS11 Paragraph 2.4.1
We note that sites were assessed for their suitability against the SFRA Level 1. Warwick District Council's SFRA is dated April 2013 and we recommend that it is updated to take into account changes in Policy (NPPF) and the revised climate
change allowances. The Environment Agency updated their guidance on how climate change could affect flood risk to new developments - 'Flood risk assessments: climate change allowances' published on gov.uk on 19th February and came into immediate effect.
The update is based new scientific evidence. The main changes are to the peak river flow allowances. We are currently preparing new guidance which can be appended to the SFRA before the examination of the Local Plan is resumed.
Cefnogi
Proposed Modifications January 2016
H43 - Kings Hill Lane
ID sylw: 69404
Derbyniwyd: 21/04/2016
Ymatebydd: Environment Agency
We have carefully reviewed the modifications proposed within the document based on the Planning Inspectors Interim Report and we find the it meets the tests of soundness:
We agree that the plan is positively prepared, justified, effective and consistent with national policy with the proposed modifications.
We have the following comments to make:
Amendments to Policy DS11 Paragraph 2.4.1
We note that sites were assessed for their suitability against the SFRA Level 1. Warwick District Council's SFRA is dated April 2013 and we recommend that it is updated to take into account changes in Policy (NPPF) and the revised climate
change allowances. The Environment Agency updated their guidance on how climate change could affect flood risk to new developments - 'Flood risk assessments: climate change allowances' published on gov.uk on 19th February and came into immediate effect.
The update is based new scientific evidence. The main changes are to the peak river flow allowances. We are currently preparing new guidance which can be appended to the SFRA before the examination of the Local Plan is resumed.
We have carefully reviewed the modifications proposed within the document based on the Planning Inspectors Interim Report and we find the it meets the tests of soundness:
We agree that the plan is positively prepared, justified, effective and consistent with national policy with the proposed modifications.
We have the following comments to make:
Modification 15
We support the wording of the proposed modification. Modification 21 - Section 1.8
The Finham Brook, a designated Main River flows through the King's Hill site H43 near the southern boundary. We would support proposals to create land for open space and this should be linked in to the provision of green and blue infrastructure. Every opportunity should be taken to create additional flood storage to reduce the risk of flooding elsewhere. Ammendments to Policy DS11 Paragraph 2.4.1
We note that sites were assessed for their suitability against the SFRA Level 1. Warwick District Council's SFRA is dated April 2013 and we recommend that it is updated to take into account changes in Policy (NPPF) and the revised climate
change allowances. The Environment Agency updated their guidance on how climate change could affect flood risk to new developments - 'Flood risk assessments: climate change allowances' published on gov.uk on 19th February and came into immediate effect.
The update is based new scientific evidence. The main changes are to the peak river flow allowances. We are currently preparing new guidance which can be appended to the SFRA before the examination of the Local Plan is resumed.