BASE HEADER

Yes

Preferred Options 2025

ID sylw: 102865

Derbyniwyd: 07/03/2025

Ymatebydd: Severn Trent Water

Crynodeb o'r Gynrychiolaeth:

This development will likely require treatment at Alcester (STW) Treatment Works, this Wastewater Treatment Works has low capacity constraints and low environmental constraints. Due to the size of the development, it is recommended that network upgrades and infrastructure upgrades will be required, alongside hydraulic modelling and engagement with STW. Overall this development site is considered a lower risk location.