BASE HEADER

Other

Preferred Options 2025

ID sylw: 102931

Derbyniwyd: 07/03/2025

Ymatebydd: Severn Trent Water

Crynodeb o'r Gynrychiolaeth:

This development will likely require treatment at Wootton Wawen (STW) Treatment Works, this Wastewater Treatment Works has low capacity constraints and high environmental constraints. Due to the size of the development, it is recommended that network upgrades will be required, alongside hydraulic modelling and engagement with STW. There could potentially be an alternative connection to Redditch - Spernal (STW) Treatment works however there are network constraints due to significant distance from the development site. Overall this development site is considered a medium risk location, as there is capacity however infrastructure upgrades will be required.