This development site will likely require treatment at Itchen Bank (STW) Treatment Works, this Wastewater Treatment Works has medium capacity and very high environmental constraints. Network constraints as distance to nearest available WWTW with available capacity is 2.5km, therefore significant infrastructure upgrades are required and there are significant costs associated with this. Overall this development site is considered a high risk location, there is some capacity however in order to accommodate growth, infrastructure upgrades will be required and we would need to work closely to understand build timelines, in order to plan accordingly.