ID sylw: 107053

Derbyniwyd: 03/03/2025

Ymatebydd: National Grid Electricity Distribution (South West) PLC

Asiant : Lucy White Planning Limited

Crynodeb o'r Gynrychiolaeth:

This potential location is affected by a 132kV overhead electricity line, strategically important utility infrastructure serving Warwick and Royal Leamington Spa and the wider area. NGED does not object to development, providing this infrastructure is safeguarded. Early consideration of the line through the masterplanning process is critical to ensure the line can be appropriately incorporated into planned development.

Proposals for major development will rely on adequate capacity within the national grid to meet the increased demand for electricity. Please ensure early engagement with NGED to establish existing capacity and any enhancements, including sub-stations, required to accommodate the planned growth.