ID sylw: 108447
Derbyniwyd: 06/03/2025
Ymatebydd: Mr R Wilding
Asiant : Cerda Planning Ltd
Site 623
Land ownership – single freehold land owner, intention to bring land forward for residential development immediately, discussions ongoing with promoters and housebuilders, developer interest high.
Site capacity – Up to 48 dwellings.
On site infrastructure delivery – blue and green infrastructure, biodiversity net gain, linkages to connect in with existing non car travel routes in urban area, affordable housing, public open space in a range of typologies.
Off site infrastructure delivery – layout to ‘forward face’ and integrate with urban area and adjacent land parcels and/or open countryside, junction improvements as determined by strategic transport modelling and site specific Transport Assessment, travel plans and a package of sustainable transport improvements, education contributions, health contributions. Other contributions to be assessed through SWLP evidence base and emerging policy framework.
Viability – no issues identified.
Delivery timescales – As follows;
•Submission of outline application – January 2026
•Outline granted – July 2026
•Submission of 1st Reserved Matters - December 2026
•Discharge of outline conditions - May 2027
•Reserved Matters approval - July 2027
•Discharge of conditions January - December 2027
•Start on Site (SoS) - May 2028 (following S184 / S278 technical approval)
•Plots delivered from September 2028