Gwrthwynebu
Publication Draft
ID sylw: 65992
Derbyniwyd: 27/06/2014
Ymatebydd: Barwood Development Securities Ltd
Asiant : HOW Planning LLP
Cydymffurfio â’r gyfraith? Heb nodi
Cadarn? Nac Ydi
Dyletswydd i gydweithredu? Heb nodi
Barwood object to the inflexible approach taken to bringing forward allocated sites
in the Growth Villages through Policy H10.
Barwood consider that the approach taken in clause (c) is overly restrictive. By the very fact that the Council has allocated a site for development, the site's
deliverability is reinforced. The Council should not therefore put a limit of the
number of dwellings which can be delivered per annum. This approach is
restrictive and does not follow the Framework's positive growth message.
Barwood suggest that this clause is removed from the Policy H10.
See attachment