BASE HEADER

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68389

Derbyniwyd: 22/04/2016

Ymatebydd: Cryfield Land (Kenilworth) Ltd

Asiant : Mr Niall Crabb

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Nac Ydi

Crynodeb o'r Gynrychiolaeth:

At 2.83, it is stated that other known issues will be resolved by way of a Plan Review. If the issue is known about it should be resolved NOW and certainly as part of the current Examination of the Plan, including its soundness.
This particularly applies to the area South of Coventry where, apart from the need for flexibility to meet unmet demand, the allocated sites are not believed to be based on objective analysis. Land at Cryfield/Gibbet Hill is available to meet demand and should not be ignored for a subsequent Review with less public input.

Testun llawn:

At 2.83, it is stated that other known issues will be resolved by way of a Plan Review. If the issue is known about it should be resolved NOW and certainly as part of the current Examination of the Plan, including its soundness.
This particularly applies to the area South of Coventry where, apart from the need for flexibility to meet unmet demand, the allocated sites are not believed to be based on objective analysis. Land at Cryfield/Gibbet Hill is available to meet demand and should not be ignored for a subsequent Review with less public input.