BASE HEADER
RDS1: The Council is adopting an Interim Level of Growth of 12,300 homes between 2011 and 2029
Gwrthwynebu
Revised Development Strategy
ID sylw: 55203
Derbyniwyd: 21/07/2013
Ymatebydd: Paul and Caroline Whitwood
Objects to the RDS. Concerned with these proposals and believe them to be wholly inappropriate and an unfair burden on the small areas of Warwick district that will be affected by these developments. Expects response to all concerns in detail, justifying the RDS with factual and appropriate data.
Housing requirements based upon the natural growth of the population indicates that only circa 5,500 new houses are required and not the 12,300 being proposed. A recent housing needs survey in Bishops Tachbrook identified a total housing need of 15 additional properties (from a response rate of 500 homes from a total of 750 in the village). So based upon this, why are so many houses being proposed in the locality of the village? Building an artificially high number of houses will simply encourage more migration to an area which is a nicer place to live than many inner city urban areas.
Building an excess of new houses will promote more commuting which is something that is already causing a major problem in the area through traffic congestion.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55210
Derbyniwyd: 26/07/2013
Ymatebydd: Anne Brar
The projected housing needs of 12,300 new homes to be built is much too high and cannot be justified.
The alternative is to lower the housing to be built to meet local needs, and especially houses that local people could afford.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55224
Derbyniwyd: 26/07/2013
Ymatebydd: Frans Vlemmiks
The RDS advocates 12,000 new houses over the period of the plan, when the number required to meet the additional needs based on 2001 and 2011 census plus the increase in Warwick over recent years would indicate a figure of the order of 5,500.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55234
Derbyniwyd: 26/07/2013
Ymatebydd: Mr Patrick Reddin
The projected 12,300 homes are extremely high and understands that less than half that number would meet local needs. There are a large number of empty houses in Warwick and Leamington, could these be used to house people instead of just building more new ones?
Should there not be a slower phasing in of housing based on estimated local demand releasing land as demand grows rather than an optimistic estimate so far into the future?
With the current and projected Government cutbacks, will the Council have the funding to expand the needed infrastructure to support 12,300 homes?
From the meetings it appears that a realistic forecast of need would mean that we already have the required five year supply of sites when you balance housing with employment growth forecasts vs the housing market. Why has this not been taken into consideration in the local plan?
Gwrthwynebu
Revised Development Strategy
ID sylw: 55236
Derbyniwyd: 26/07/2013
Ymatebydd: Mrs Christine Miles
Any plan should accurately reflect the population growth and demand within the district taking into account the latest data from ONS. The proposed plan massively overstates the demand.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55240
Derbyniwyd: 26/07/2013
Ymatebydd: Patricia Vlemmiks
The RDS advocates 12,000 new houses over the period of the plan, when the number required to meet the additional needs based on 2001 and 2011 census plus the increase in Warwick over recent years would indicate a figure of the order of 5,500.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55248
Derbyniwyd: 26/07/2013
Ymatebydd: Lynn Waters
The number of houses appears to be significantly overstated and concentrated to the south of Warwick along Gallows Hill area rather than being spread more evenly (even if the number of houses required is a correct projection). Projections are estimates and surely it is better to make smaller incremental changes rather than sweeping over-reaching change, which may not be needed or desirable.
The density of development means that the very features that attract people to live in Warwickshire will be lost and the developments will just become co-joined and akin to Milton Keynes or similar, with no distinction between the different sub areas and villages.
The attraction of Warwickshire is farmland between and surrounding the town and villages adjacent to Warwick and Leamington, providing space and definition to the residential areas. People who live in Warwick District do not want to live in a housing / pseudo town sprawl. Towns and villages evolve they are not dropped into some Greenfields.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55253
Derbyniwyd: 29/07/2013
Ymatebydd: Mrs Barbara Winstone
Opposed to the level of development planned for Warwick and the area to the south. Understands there is a need for housing development and that many first time buyers cannot find affordable housing. The new planned housing is not aimed at these people in the main. The likelihood is that these houses would attract people from urban centres aiming to live in the country while continuing to work in the urban areas. Soon our countryside will also be urban. When road congestion and environmental concerns are seen as detrimental to the health of the planet you will be adding to both as people commute to work. How many properties already in existence in towns and cities are unoccupied, what sites could be redeveloped?
Gwrthwynebu
Revised Development Strategy
ID sylw: 55258
Derbyniwyd: 26/07/2013
Ymatebydd: The Leamington Society
Progress towards the Plan is crucial but the Plan will be of little benefit unless it sets clear and specific criteria for shaping the District's development. We seek firmer guidelines for development within the Plan period.
Half of the potential growth derives from predictions of inward migration to the District. These projections are fraught with uncertainty, as the ONS warns. There is a danger that the Local Plan confuses supply and demand. Building a lot of extra houses will attract immigrants to occupy them. This might appear to be meeting demand, but the demand is a response to supply and not the other way round.
ONS provide separate figures, for "natural" growth and for migration, only as far ahead as 2021. Beyond that there is simply an aggregate projection, for the years 2021 - 2031. The latest projections are for just over 1,000 extra people per year in the District. But the ONS systems round their figures to the nearest 1,000, which could include any number between 501-1499. There is therefore a huge potential variation in the total as the annual figures accumulate over the Plan period for Warwick District.
Good, realistic planning would provide flexibility to track progress during the plan period and criteria to respond appropriately. Rather than simply being reactive to individual applications, the Plan should set a hierarchy of priorities towards achieving the District's housing needs, with sequential choice assigned to key objectives.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55260
Derbyniwyd: 29/08/2013
Ymatebydd: Bloor Homes
Asiant : Marrons Planning
Unable to comment on whether it considers this proposal would meet the requirements of paragraph 182 of the Framework in respect of meeting the full and objectively assessed needs in the housing market area.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55283
Derbyniwyd: 29/07/2013
Ymatebydd: Gavin & Sheila Tilstone & Holden
There is more housing planned than actually required which would increase the population by 20%. A study by Warwick's own consultants gave a figure of 4405 new homes being required.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55306
Derbyniwyd: 28/07/2013
Ymatebydd: Jenny Hornsby
Population growth from 1991 to 2011 was 18%. Now a further 20% increase in 15 years is suggested, requiring 12,300 new homes. Using natural growth rates and an allowance for migration only 5,400 homes are really required. The Council's Economic and Demographic Forecast Study (December 2012), which in option PROJ 5 suggested 4,405 new homes were required. Why is this being ignored?
Warwick District has unemployment rate of 1.7%. The 2012 Strategic Housing Market Assessment stated that overall 'Warwick District had a very good job-homes balance'. Therefore, new homes being the driver for new jobs is not a valid reason.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55315
Derbyniwyd: 07/08/2013
Ymatebydd: Budbrooke Parish Council
Regards the overall estimated residential development growth in the Local Plan to be significantly out of proportion to the local need.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55323
Derbyniwyd: 29/07/2013
Ymatebydd: Ray & Marion Bullen
The existing 2007 local plan is not to be considered out‑of‑date simply because it was adopted prior to the publication of this Framework; Policies contained in NPPF are material considerations which local planning authorities should take into account and must also be taken into account in the preparation of plans: due weight should be given to relevant policies in existing plans according to their degree of consistency with this framework
The existing local plan adopted in 2007 following a Public Inquiry during 2006 into objections to the proposed plan. The Inspector produced a 562 page report. Some of the issues are relevant to the new local plan proposals. It settled many questions of concern for the community, in effect setting a contract with the community, upon which many people made decisions about their lifestyle arrangements. The RDS with a dramatic change to the size of the district and the concentration of very large amounts of new housing on land that is currently subject to Rural Area policies, is seen by many as a breach of that contract. As a result there is much concern and indeed, anger, at the proposals being consulted on and in the way that the door has been left open by the Council for planning applications to be made that negate the purpose of any local plan and the consultation process to establish it.
The purpose of Local Government is to serve the community in the district that it covers. It is not to impose in a dictatorial manner changes that will erode the quality of life of those that live in that District unless there should be a very good set of reasons that carry greater weight than maintaining and improving the Strategic vision of the authority. At the many meetings in the last 6 weeks, not found anyone that supports the proposals.
Key findings of the inspector (about the plan after 2011): Council is able to show that there is no need to identify further housing sites; The balance of 2,210 dwellings to be provided between 2005 and 2021 equates to 138 dwellings per year; Satisfied that the Council is justified in not identifying sites to meet the requirement to 2021; Residual housing requirement for the period 2005-2021 can be met - RSS housing requirement 2001 - 2021: 8,091, Dwellings completed 2001 to 2005: 3,324, Remaining dwellings to be provided: 4,767.
By the end of 2011/12 the dwellings completed had increased to 6,084. Deducted from the original requirements this leaves 2,007 remaining to be provided by 2021. If 2,007 is the plan for 10 years, then for 18 years until 2029 it might be 200x18= 3,600. The latest Hearn figure for the 18 years is 8,500 persons or 3,705 dwellings, so it looks as though we should be getting back the anticipated plan. This ties in with census findings: 21.74% increase in households compares with 15.32% over the whole of England for the same 20 year period. The District has done more than most.
How did 2,007 become 12,300? In 2008 the RSS came up with a figure of 8,300 for the next 20 years up to 2029. The banking and economic crisis followed, a change of government, abolition of the RSS. Views were sought from the public and 58% agreed low growth. The first consultation was for 10,800 homes, higher than the RSS. This was rejected by 87% of respondents. A reasoned assessment based on ONS data was done that indicated a figure of 5,400 homes by 2029 was the housing need for the locality. Localism Act 2011, giving local people a chance to influence the way that development grew.
The plan so far fails to meet NPPF requirements (para 150-155). The vision and aspirations of the local communities, the definition and implementation of sustainable development to achieve net gains on all three dimensions thereof avoiding adverse impacts on any are not only not demonstrated, they seem to be ignored. Local plans should be aspirational but realistic and address the spatial implications of change.
If 2,007 homes by 2021 was considered to be realistic by the Inspector in 2006/7, and shown to be so by the District council at the time, what are the reasons for the unrealistic numbers now? A wide section of the community is engaged and would wish that it was proactively so. But this requires a listening district council.
In December 2012, the Economic and Demographic Forecasts Study prepared by GL Hearn updated the forecast for population growth. Until the joint SHMA is received, the 12,300 household cannot be considered as a valid consultation. Across the neighbouring authorities, jobs ought to follow unemployment so far as it is sensible to do. Since our unemployment count is very low, and job availability is still very fragile, then building a larger volume of homes than we have ever done does not seem to be a good strategy. It could give us a dramatic employment problem.
Maybe part of the plan is to grow homes to get new homes bonus, but this is not a material consideration in NPPF terms. It is not a good business plan either, because the infrastructure needed to support a 29,000 or so population increase has yet to be provided. The CIL paper acknowledges that there will be a funding gap unspecified. There could be a £100m capital cost shortfall between total public infrastructure costs (County, District, NHS, & central government) compared with CIL, section 106 and other charges to the developers after accounting for 40% number reduction for CIL-less affordable housing and approvals already given.
With a reduced housing target of 5,400 the infrastructure need would to be less because it is a smaller volume and can be spread more evenly around the district spreading not concentrating infrastructure overload.
Strongly request that you reconsider the quantity of housing needed by the plan, limiting it to no more than 5,400 homes by 2029. This will produce all the homes needed by the locality, gives achievable 5yr land supplies through the plan period, reduces the infrastructure cost and spreads traffic volumes, avoids the need to take valuable greenfield sites and restores the confidence of the electorate in the local authority. It has been produced as an objective assessment, that takes all the requirements of the NPPF as well ONS projections into account, establishes a realistic employment strategy that recognises greater problems in neighbouring areas but allows a controlled and realistic amount of economic growth. That should then mean that we have a sustainable local plan that will fit well into the limited space we have available.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55327
Derbyniwyd: 29/07/2013
Ymatebydd: Mr John Fletcher
The perceived demand for housing is based on false data and the aspirations of, and pressures brought on the Council by developers and central government, with no regard for local needs or the wishes of residents.
The number of new houses proposed is twice that required to meet local demand. The demand data used is an extrapolation of past house building in a boom period when mortgages were easy to obtain, and bears no resemblance to actual demand in the current economic climate.
Half the sites proposed for development are on greenfield land to the south of the built-up areas of Warwick and Leamington, and would thus require the new residents to travel through these two towns to the new expected employment sites south of Coventry.
Revise downwards the quantity of new housing proposed.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55332
Derbyniwyd: 29/07/2013
Ymatebydd: Rugby Borough Council
Until the completion of the joint SHMA and the implications of the study are
discussed between the authorities, Rugby Borough Council are unable to make any
comments regarding the soundness of the document at this moment in time.
Cefnogi
Revised Development Strategy
ID sylw: 55334
Derbyniwyd: 30/07/2013
Ymatebydd: Warwickshire Police
The higher level of housing provision reflects a realistic expectation of demand.
Highlights the potential for 12,300 new homes in Warwick District. This represents an increase of approximately 23% increase in the District and approximately 5.4% increase in Warwickshire as a whole. It is logical to conclude that this will lead to a proportional increase in demand to policing services. This is in addition to significant housing growth elsewhere in the Warwickshire policing area. Accordingly, the Warwickshire Police infrastructure will require expansion in response to the planned housing and other development growth in Warwick District.
Whilst this will not, in most cases, lead to the visible structures of new police stations, there remains a fundamental requirement to provision expanded infrastructure capability in policing through mobility (police vehicles), communications (radio systems and IT infrastructure), support functions (crime recording, strategic planning, judicial services, HR, Finance, Fleet Management, Estates and others). Wherever possible these will be developed in partnership with other agencies, and should be a core component of CIL planning.
The significant growth in housing, employment and population requires continued engagement between the Council and Warwickshire Police in infrastructure planning and CIL scheduling to ensure proportional provision of flexible police infrastructure into the future.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55353
Derbyniwyd: 31/07/2013
Ymatebydd: Conservation Advisory Forum
Concerns about impact of scale of development on Warwick . There will be a 40% increase in the population of Warwick which will have a dramatic effect on the existing settlement and on traffic passing through both Warwick and also Leamington along Europa Way.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55388
Derbyniwyd: 26/07/2013
Ymatebydd: Home Builders Federation Ltd
Housing Numbers: Since the revocation of West Midlands RSS the overall proposed housing provision across the region is estimated to have fallen by 8%. RDS para 1.3 states the Council is awaiting the outcome of a new SHMA, therefore important that the Council does not assume that strategic pressures do not exist. The "What Homes Where?" toolkit suggests a higher figure of 15,557 new households over the plan period. When this higher number of households is converted into a likely dwelling requirement, the provision of only 12,300 new homes would seem to be a substantial under estimation of housing needs. The Council may wish to consider using the "How Many Homes / What Homes Where" toolkit.
RDS suggests an over reliance on the 2011-based statistics and the Council should be cautioned against any attempts to use these latest figures to justify low housing requirements in the Local Plan. The Council should refer to the Cambridge Centre for Housing & Planning Research (CCHPR) report "Choice of Assumptions in Forecasting Housing Requirements Methodological Notes" dated March 2013, which advises against the downward revision of projected population / household figures.
At this time, the Council's main evidence source is the Warwick DC SHMA Final Report dated March 2012 which is not an NPPF compliant SHMA.
Housing supply: NPPF emphasises that local planning authorities should continue to demonstrate a 5 year housing land supply, which is to be supplemented by an additional buffer of 5% to ensure choice and competition in the land market or where there has been a record of consistent under delivery of housing an additional buffer of 20%. RDS states that at present there is not a 5 year supply of land for housing within the District as required by the NPPF. Without a 5 year housing land supply, the Council will have to identify and release more development land in a wider range of locations or formulate a strategy to bring forward sites from later in the plan period sooner. The Plan needs to demonstrate maximum flexibility to ensure delivery of an objectively assessed housing need in accordance with NPPF.
The consultation makes no reference to the provision of 5% or 20% buffer in its land supply, which the Council must address to be compliant with Paragraph 47 of the NPPF.
Viability: To be compliant with the NPPF, development should not be subject to such a scale of obligations and policy burdens that viability is threatened. Council will need to justify the infrastructure requirements via the preparation of an Infrastructure Delivery Plan. Unfortunately there are a number of concerns about the assumptions used in the Council's viability assessment, which do not correlate with the recommendations of the Harman Report. As a consequence there is potentially a significant under estimation of actual costs of particular concern are build costs, costs for Code for Sustainable Homes, cost for Lifetime Homes standards, finance costs, professional fees, sales & marketing costs and S 106 contribution payments.
In Section 5 of the RDS 40% affordable housing provision with at least 25% of housing built to Lifetime Homes standards is proposed. However even with the under estimated cost inputs this proposal is not justified by the viability assessments, which demonstrate that at the Baseline Market Position no development was viable at 40% affordable housing provision.
On Sustainable Urban Extension sites (66% of the proposed land supply) at the Baseline Market Position only between 0 - 25% affordable housing provision was possible. Recommendation in paragraph 10.8 of the Affordable Housing Viability Assessment should be considered by the Council. Council should be mindful that it is inappropriate to set unachievable policy obligations.
The Council should cross reference The Affordable Housing Viability Assessment Final Report against the Community Infrastructure Levy Viability Study Final Report dated June 2013 to identify any inconsistencies between the two reports. Paragraphs 6.18 - 6.27 of the CIL Viability Study are very confusing. It is not obvious the amount of affordable housing provision achievable given the proposed CIL charges for each of the three residential CIL charging zones. The Council must clarify the proposed CIL charges and its affordable housing policy. Then the viability testing of both requirements should be synchronised.
Cefnogi
Revised Development Strategy
ID sylw: 55390
Derbyniwyd: 29/07/2013
Ymatebydd: Matthew Greene
The generation born 1980 to 1995 have been and will continue to be hit badly by the recession and budget cuts of the last few years; difficulties are faced by most people in their 20s to find affordable housing in a nice area and close to employment.
In favour of building more homes in Warwickshire to help ease the excess demand on the housing system and help to smooth out house prices throughout the area. Accepts it is difficult to build vast housing estates on greenbelt land. Understandable why Council looking to the south.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55399
Derbyniwyd: 29/07/2013
Ymatebydd: Gleeson Developlments Ltd and Sundial Group
Asiant : Savills (L&P) Ltd
Question why the Council has consulted on the RDS at this stage (on basis of interim housing figures) , rather than waiting for the updated SHMA to be completed? Reserve our right to comment on the revised housing figure when the new SHMA is published later in 2013 and encourage the Council to formerly consult once again at that time.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55402
Derbyniwyd: 29/07/2013
Ymatebydd: Police and Crime Commissioner for Warwickshire
Asiant : BB Architecture + Planning
The higher level of housing provision reflects a realistic expectation of demand. However, the inclusion of significant windfall provision through the plan period should not exclude the contribution which can be made within larger settlements in the green belt such as Leek Wootton, accordingly -
As provided by paragraph 86 of the Framework, nucleated and compact settlements such as Leek Wootton which make no contribution to the openness of the green belt should no
longer be washed over by green belt policy (this being the position in the preceding Local Plan
Gwrthwynebu
Revised Development Strategy
ID sylw: 55414
Derbyniwyd: 29/07/2013
Ymatebydd: Councillor Philip Morris
The number of new homes proposed to be built between 2011 and 2029 has been greatly over-estimated at 12,300.
These numbers place an unreasonable burden on Warwick District and assume only a significant net immigration from surrounding cities such as Coventry and Birmingham.
They are not designed to accommodate core growth of Warwick District itself. As such the development is unsustainable and contrary to good development as required by the NPPF.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55421
Derbyniwyd: 13/08/2013
Ymatebydd: Catseby Estates Ltd
Asiant : Framptons
Interim Housing Figure:
The Revised Strategy is adopting an interim figure of 12,300 homes over a plan period extending to 2029.
This may be revised pending the findings of the Joint SMA and the resulting co-operation between authorities.'
It should not be assumed that the potential revision may be required only in response to the outcome of the Joint SMA.
The RDS contains no robust evidence as to how the proposed interim level of housing satisfies the requirements of paragraph 47 of the Framework, especially when the Government is 'committed to securing economic growth in order to create jobs, and prosperity, building upon the country's inherent strengths, and to meeting the twin challenge of global competition and of a low carbon future' (Framework para 18).
It is submitted that the RDS would, if submitted for Examination, fail all tests of soundness set out at paragraph 182 of the Framework.
Housing provision arising from the housing needs of Coventry
Following the Inspectors comments on the recent Coventry Core Strategy Examination regarding the soundness of the City's housing target, a Joint SHMA is being undertaken.
The outcome of the SHMA prepared pursuant to the guidance at paras 178 - 181 of the Framework may be a requirement for a spatial response from within Warwick District to address the shortfalls within Coventry City to meet its housing requirements quantitatively and qualitatively.
Coventry City has recognised for some period of time that it is not able to provide sufficient housing choice in location of housing land, particularly in the form of 'aspirational housing' to support the drive for inward investment and economic growth in the city.
Kenilworth is well placed to accommodate some of this additional housing need, particularly in view of its proximity to Coventry, and transportation connections - road and shortly rail.
It is understood that the rail station at Kenilworth should be open by the end of 2016 (Patrick McLoughin, Secretary of State for Transport 3rd June 2016).
If it is assumed that an adopted Local Plan is achieved by the end of 2014, the Kenilworth station might reasonably be anticipated to be operational within 12 months of new homes being provided on this site.
In conclusion it is submitted that this site could usefully provide a contribution to housing requirements arising from the needs of Coventry which cannot be met within the administrative area of the city.
Additional housing provision at Kenilworth would also be well related to the now committed development at Coventry and Warwickshire Gateway.
. 4) The provision of land to meet possible future development needs beyond the plan period (Safeguarded Land) Paragraph 85 of the Framework states (second bullet point): 'When defining boundaries, local planning authorities should: * not include land which it is unnecessary to keep permanently open.' In that it is evident the strategy of the emerging Local Plan requires the release of land from the Green Belt to achieve sustainable patterns of development, it is almost inconceivable that a future strategy will not similarly require further releases of land from the Green Belt. In order to make provision for longer term development needs, this Local Plan should identify 'Safeguarded Land'. If contrary to the submissions that have been made above, it is concluded that this site is not required to meet housing needs arising from within the plan period, then it is submitted that the site should be excluded from the Green Belt to meet possible future development requirements beyond the Plan period.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55427
Derbyniwyd: 29/07/2013
Ymatebydd: Federal Mogul
Asiant : Pro Vision
Supports the overall level of development but queries whether it is enough to effect the step change in housing development now required in government policy.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55431
Derbyniwyd: 03/08/2013
Ymatebydd: John Ludlow
Local towns unable to handle current peak time traffic volumes without adding several more thousand houses. Also local schools and hospitals are at or very near capacity with no plans to increase capacity.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55432
Derbyniwyd: 29/07/2013
Ymatebydd: Commercial Estates Group
Asiant : Nathaniel Lichfield & Partners
Object on the basis that it is not appropriate to produce an interim housing figure. The housing requirement should be based on up to date evidence. Aware this is being prepared and the local plan preparation should await the findings of the housing study.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55433
Derbyniwyd: 29/07/2013
Ymatebydd: CALA Homes (midlands) Ltd & Kenilworth Golf Club
Asiant : Cerda Planning Ltd
Policy RDS 1 is concerned with delivering an appropriate level of housing growth across the District. It is -presently noted as an interim figure, at 12,300 homes.
It is welcomed that the Council recognise that interim housing figure -could and should change as result of more up to date evidence as it emerges.
Important however that the Council recognise the important provisions of the NPPF, in particular the -need to meet the full objectively assessed housing needs, and the need to boost significantly the supply of -housing.
The Council are therefore invited to re-assess housing figures increasing the requirements to reflect the historical -local growth; apply the ONS figures with some caution; and recognise the important requirement to meet the -full objectively assessed housing need.
This will be a matter scrutinized in detail at Examination.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55434
Derbyniwyd: 29/07/2013
Ymatebydd: Centaur Properties
Asiant : Cerda Planning Ltd
Policy RDS 1 is concerned with delivering an appropriate level of housing growth across the District. It is -presently noted as an interim figure, at 12,300 homes.
It is welcomed that the Council recognise that interim housing figure -could and should change as result of more up to date evidence as it emerges.
Important however that the Council recognise the important provisions of the NPPF, in particular the -need to meet the full objectively assessed housing needs, and the need to boost significantly the supply of -housing.
The Council are therefore invited to re-assess housing figures increasing the requirements to reflect the historical -local growth; apply the ONS figures with some caution; and recognise the important requirement to meet the -full objectively assessed housing need.
This will be a matter scrutinized in detail at Examination.
Gwrthwynebu
Revised Development Strategy
ID sylw: 55436
Derbyniwyd: 29/07/2013
Ymatebydd: CALA Homes (Midlands) Ltd & Mr & mrs Watkinson
Asiant : Cerda Planning Ltd
Policy RDS 1 is concerned with delivering an appropriate level of housing growth across the District. It is -presently noted as an interim figure, at 12,300 homes.
It is welcomed that the Council recognise that interim housing figure -could and should change as result of more up to date evidence as it emerges.
Important however that the Council recognise the important provisions of the NPPF, in particular the -need to meet the full objectively assessed housing needs, and the need to boost significantly the supply of -housing.
The Council are therefore invited to re-assess housing figures increasing the requirements to reflect the historical -local growth; apply the ONS figures with some caution; and recognise the important requirement to meet the -full objectively assessed housing need.
This will be a matter scrutinized in detail at Examination.