Strategic Growth Location SG11 Question

ID sylw: 102758

Derbyniwyd: 07/03/2025

Ymatebydd: Severn Trent Water

Crynodeb o'r Gynrychiolaeth:

This development will likely require treatment at Warwick - Longbridge (STW) Treatment Works, this Wastewater Treatment Works has medium capacity and high environmental constraints. Due to the size of the development, it is recommended that network upgrades will be required, alongside hydraulic modelling and engagement with STW. Overall this development site is considered a medium/high risk location, there is some capacity however in order to accommodate growth, infrastructure upgrades will be required and we would need to work closely to understand build timelines, in order to plan accordingly.

Other

Preferred Options 2025

Strategic Growth Location SG12 Question

ID sylw: 102775

Derbyniwyd: 07/03/2025

Ymatebydd: Severn Trent Water

Crynodeb o'r Gynrychiolaeth:

This development site will likely require treatment at Itchen Bank (STW) Treatment Works, this Wastewater Treatment Works has medium capacity and very high environmental constraints. Due to the size of the development, it is recommended that network upgrades will be required, alongside hydraulic modelling and engagement with STW. Overall this development site is considered a high risk location, there is some capacity however in order to accommodate growth, infrastructure upgrades will be required and we would need to work closely to understand build timelines, in order to plan accordingly.

Other

Preferred Options 2025

Strategic Growth Location SG13 Question

ID sylw: 102783

Derbyniwyd: 07/03/2025

Ymatebydd: Severn Trent Water

Crynodeb o'r Gynrychiolaeth:

This development will likely require treatment at Warwick - Longbridge (STW) Treatment Works, this Wastewater Treatment Works has medium capacity constraints and high environmental constraints. Due to the size of the development, it is recommended that network upgrades will be required, alongside hydraulic modelling and engagement with STW. Overall this development site is considered a medium/high risk location, there is some capacity however in order to accommodate growth, infrastructure upgrades will be required and we would need to work closely to understand build timelines, in order to plan accordingly.

Other

Preferred Options 2025

Strategic Growth Location SG14 Question

ID sylw: 102789

Derbyniwyd: 07/03/2025

Ymatebydd: Severn Trent Water

Crynodeb o'r Gynrychiolaeth:

This development will likely require treatment at Warwick - Longbridge (STW) Treatment Works, this Wastewater Treatment works has medium capacity constraints and high environmental constraints. Due to the size of the development, it is recommended that network upgrades will be required, alongside hydraulic modelling and engagement with STW. Overall this development site is considered a medium/high risk location, there is some capacity however in order to accommodate growth, infrastructure upgrades will be required and we would need to work closely to understand build timelines, in order to plan accordingly.

No

Preferred Options 2025

Strategic Growth Location SG15 Question

ID sylw: 102806

Derbyniwyd: 07/03/2025

Ymatebydd: Severn Trent Water

Crynodeb o'r Gynrychiolaeth:

This development will likely require treatment at Wellesbourne (STW) Treatment Works, this Wastewater Treatment works has very high capacity constraints and high environmental constraints. Due to the size of the development, it is recommended that network upgrades will be required, alongside hydraulic modelling and engagement with STW. As this site has very high capacity and environmental constraints, it is recommended to avoid this site. Overall this development site is considered a very high risk location.

No

Preferred Options 2025

Strategic Growth Location SG16 Question

ID sylw: 102808

Derbyniwyd: 07/03/2025

Ymatebydd: Severn Trent Water

Crynodeb o'r Gynrychiolaeth:

This development will likely require treatment at Wellesbourne (STW) Treatment Works, this Wastewater Treatment works has very high capacity constraints and high environmental constraints. Due to the size of the development, it is recommended that network upgrades will be required, alongside hydraulic modelling and engagement with STW. As this site has very high capacity and environmental constraints, it is recommended to avoid this site. Overall this development site is considered a very high risk location.

Other

Preferred Options 2025

Strategic Growth Location SG17 Question

ID sylw: 102820

Derbyniwyd: 07/03/2025

Ymatebydd: Severn Trent Water

Crynodeb o'r Gynrychiolaeth:

This development will likely require treatment at Shipston - Fell Mill (STW) Treatment Works, this Wastewater Treatment Works has medium capacity constraints and high environmental constraints. Due to the size of the development, it is recommended that network upgrades will be required, alongside hydraulic modelling and engagement with STW. To accommodate growth at this site, extensive wastewater treatment works upgrades would be required. Overall this development site is considered a high risk location.

Yes

Preferred Options 2025

Strategic Growth Location SG18 Question

ID sylw: 102826

Derbyniwyd: 07/03/2025

Ymatebydd: Severn Trent Water

Crynodeb o'r Gynrychiolaeth:

This development will likely require treatment at Stratford - Milcote (STW) Treatment Works, this Wastewater Treatment Works has low capacity constraints and low environmental constraints. Due to the size of the development, it is recommended that network upgrades will be required, alongside hydraulic modelling and engagement with STW. Overall this development site is considered a lower risk location.

Yes

Preferred Options 2025

Strategic Growth Location SG19 Question

ID sylw: 102831

Derbyniwyd: 07/03/2025

Ymatebydd: Severn Trent Water

Crynodeb o'r Gynrychiolaeth:

This development will likely require treatment at Stratford - Milcote (STW) Treatment Works, this Wastewater Treatment Works has low capacity constraints and low environmental constraints. Due to the size of the development, it is recommended that network upgrades will be required, alongside hydraulic modelling and engagement with STW. Overall this development site is considered a lower risk location.

Other

Preferred Options 2025

Strategic Growth Location SG20 Question

ID sylw: 102841

Derbyniwyd: 07/03/2025

Ymatebydd: Severn Trent Water

Crynodeb o'r Gynrychiolaeth:

This development will likely require treatment at Bidford - on - Avon (STW) Treatment Works, this Wastewater Treatment Works has very high capacity constraints and medium environmental constraints. Due to the size of the development, it is recommended that network upgrades will be required, alongside hydraulic modelling and engagement with STW. To accommodate growth at this site, extensive wastewater treatment works upgrades would be required. Overall this development site is considered a high risk location.