Results for Severn Trent Water search
New searchOther
Preferred Options 2025
Potential Settlement Question F2
Representation ID: 103040
Received: 07/03/2025
Respondent: Severn Trent Water
This development site will likely require treatment at Itchen Bank (STW) Treatment Works, this Wastewater Treatment Works has medium capacity and very high environmental constraints. Due to the size of the development, it is recommended that network upgrades will be required, alongside hydraulic modelling and engagement with STW. Overall this development site is considered a medium/high risk location, there is some capacity however in order to accommodate growth, infrastructure upgrades will be required and we would need to work closely to understand build timelines, in order to plan accordingly.
Other
Preferred Options 2025
Potential Settlement Question F3
Representation ID: 103051
Received: 07/03/2025
Respondent: Severn Trent Water
This development site will likely require treatment at Itchen Bank (STW) Treatment Works, this Wastewater Treatment Works has medium capacity and very high environmental constraints. There are network constraints as the distance to the nearest available WWTW with available capacity is 2km, therefore significant infrastructure upgrades are required and there are significant costs associated with this. Overall this development site is considered a medium/high risk location, there is some capacity however in order to accommodate growth, infrastructure upgrades will be required and we would need to work closely to understand build timelines, in order to plan accordingly.
Other
Preferred Options 2025
Potential Settlement Question G1
Representation ID: 103062
Received: 07/03/2025
Respondent: Severn Trent Water
This development site will likely require treatment at Itchen Bank (STW) Treatment Works, this Wastewater Treatment Works has medium capacity and very high environmental constraints. Network constraints as distance to nearest available WWTW with available capacity is 2.5km, therefore significant infrastructure upgrades are required and there are significant costs associated with this. Overall this development site is considered a high risk location, there is some capacity however in order to accommodate growth, infrastructure upgrades will be required and we would need to work closely to understand build timelines, in order to plan accordingly.
Other
Preferred Options 2025
Potential Settlement Question X1
Representation ID: 103074
Received: 07/03/2025
Respondent: Severn Trent Water
This development will likely require treatment at Warwick - Longbridge (STW) Treatment Works, this Wastewater Treatment Works has medium capacity constraints and high environmental constraints. Due to the size of the development, it is recommended that network upgrades will be required, alongside hydraulic modelling and engagement with STW. Overall this development site is considered a medium/high risk location, there is some capacity however in order to accommodate growth, infrastructure upgrades will be required and we would need to work closely to understand build timelines, in order to plan accordingly.
Other
Preferred Options 2025
Potential Settlement Question X2
Representation ID: 103083
Received: 07/03/2025
Respondent: Severn Trent Water
This development will likely require treatment at Warwick - Longbridge (STW) Treatment Works, this Wastewater Treatment works has medium capacity and high environmental constraints. Due to the size of the development, it is recommended that network upgrades will be required, alongside hydraulic modelling and engagement with STW. Overall this development site is considered a medium/high risk location, there is some capacity however in order to accommodate growth, infrastructure upgrades will be required and we would need to work closely to understand build timelines, in order to plan accordingly.
Yes
Preferred Options 2025
Potential Settlement Question BW
Representation ID: 103087
Received: 07/03/2025
Respondent: Severn Trent Water
This development will likely require treatment at Stratford - Milcote (STW) Treatment Works, this Wastewater Treatment Works has low capacity constraints and low environmental constraints. Due to the size of the development, it is recommended that network upgrades will be required, alongside hydraulic modelling and engagement with STW. Overall this development site is considered a lower risk location.
Yes
Preferred Options 2025
Do you agree with the approach laid out in Draft Policy-H- Water Efficiency?
Representation ID: 103121
Received: 07/03/2025
Respondent: Severn Trent Water
Severn Trent Water are supportive of the Water Efficiency Policy, particularly in terms of going over and beyond the requirements for water efficiency standards.
Yes
Preferred Options 2025
Do you agree with the approach laid out in Draft Policy- I- Water Supply and Wastewater Infrastructure?
Representation ID: 103141
Received: 07/03/2025
Respondent: Severn Trent Water
Severn Trent Water are supportive of the Water Supply and Wastewater Infrastructure Policy, however in the paragraph above the policy, please can you specify that the enactment of schedule 3 of the Flood and Water Management Act will remove this automatic right for new developments to connect to the existing surface water sewer system.
Yes
Preferred Options 2025
Do you agree with the approach laid out in Draft Policy- K- Multifunctional Sustainable Drainage Systems (SuDS)?
Representation ID: 103152
Received: 07/03/2025
Respondent: Severn Trent Water
Severn Trent Water are supportive of the Sustainable Urban Drainage Systems Policy.
Other
Preferred Options 2025
Do you agree with the approach laid out in Draft Policy Direction 14- Major Investment Sites (MIS)?
Representation ID: 103264
Received: 07/03/2025
Respondent: Severn Trent Water
Summarised comments around the MIS below -
MIS.1 Treatment at Warwick - Longbridge, medium capacity constraints and high environmental constraints, network and infrastructure upgrades required, considered a medium/high risk location.
MIS.2/ MIS.3 Treatment at Stafford -Milcote, low capacity constraints and low environmental constraints, network upgrades will be required, considered a lower risk location.
MIS.4/ MIS.5/ MIS.6/ MIS.7 Treatment at Coventry - Finham, medium capacity and very high environmental constraints, network and infrastructure upgrades required, considered a medium/high risk location.
MIS.8/MIS.9 Treatment at Wellesbourne, very high capacity constraints and very high environmental constraints, recommendation to avoid this site.