BASE HEADER

H43 - Kings Hill Lane

Yn dangos sylwadau a ffurflenni 1 i 30 o 42

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68296

Derbyniwyd: 17/04/2016

Ymatebydd: Finham Brook Flood Action Group

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Nac Ydi

Crynodeb o'r Gynrychiolaeth:

The Sustainability Appraisal with regard to flood risk is based on out of date data, and takes no account of recent flooding events in Kenilworth.

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68318

Derbyniwyd: 17/04/2016

Ymatebydd: Mr Alan Rock

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Nac Ydi

Crynodeb o'r Gynrychiolaeth:

I object to the development of Kings Hill Lane. My reasons for objecting are outlined below.

Overall these plans would destroy the rural character of the local area and neighbourhood, create adverse noise and disturbance affecting residents and wildlife, and breach established acts designed to protect wildlife and as such the development should not be allowed to take place.

There is a huge quantity of brown field sites in both Coventry and Warwick that could easily be developed to accommodate the quantity of housing required without destroying green belt land that once utilised will be gone forever.

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68394

Derbyniwyd: 22/04/2016

Ymatebydd: Cryfield Land (Kenilworth) Ltd

Asiant : Mr Niall Crabb

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Nac Ydi

Crynodeb o'r Gynrychiolaeth:

There is no material negative difference in the Sustainability Appraisal Report on Cryfield, in comparison to Kings Hill, that should result in it not being allocated.

It is suggested that this proves that the Appraisal which has been used to allocate new sites is not fully objective because it has not been subject to proper public debate on the pros and cons of allocated and non-allocated sites.

It is suggested that this should be undertaken as part of the reconvened Examination, in order to ensure that all possible (and suitable) sites have been properly appraised.

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68430

Derbyniwyd: 20/04/2016

Ymatebydd: Mr Paul Abberley

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Nac Ydi

Crynodeb o'r Gynrychiolaeth:

Lack of consultation. No proper media coverage and letter drops as promised by WDC.
Plan rushed through.
Historical sites and wildlife will be destroyed.
Numerous projects already planned in area. HS2 and Jag/Landover. Gridlocks and lack of infastructure.
Coventry Council has not correctly looked at land available within own area and selling land to Universities that could be used for housing.
Gap will be destroyed between Coventry and Kenilworth.
How does it fit in with "extrodinary circs" rule.

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68478

Derbyniwyd: 21/04/2016

Ymatebydd: Mrs Sue Crofts

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Nac Ydi

Crynodeb o'r Gynrychiolaeth:

If this change is made to the Local Plan it will have deleterious effects on traffic in and around the Parish of Stoneleigh. I would only be in favour of the Kings Hill development if a detailed proposal was made to improve traffic volumes and the free flow of traffic on the Birmingham Road and Coventry Road in Stoneleigh village.

Improvements such as a small bypass, one way traffic through the village and one way traffic over Stoneleigh Bridge have been discussed by Parishioners as appropriate alternative measures.

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68521

Derbyniwyd: 22/04/2016

Ymatebydd: Mr Martin Smith

Cydymffurfio â’r gyfraith? Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Ydi

Crynodeb o'r Gynrychiolaeth:

It is very clear that this could become a major development site. Without adequate prior infrastructure, this could effectively disrupt local services, facilities etc. As a resident of Stoneleigh with a growing traffic issue, we do not want any more traffic routing through the village, in fact we want less.Consideration has to be given to the route and connection Leamington to Coventry direction avoiding th Kenilworth Rd / A46 which routes traffic over Stoneleigh Bridge and through the village.

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68530

Derbyniwyd: 22/04/2016

Ymatebydd: Diane Francis

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Nac Ydi

Crynodeb o'r Gynrychiolaeth:

Road improvements need to be planned and put into place before you can consider building so many houses within the vicinity of our village

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68557

Derbyniwyd: 22/04/2016

Ymatebydd: Todd Williams

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Nac Ydi

Crynodeb o'r Gynrychiolaeth:

H43 Kings Hill Lane proposal is unsound and fails to comply with the duty to co-operate. WDC has worked with CCC in a very closed manner to rush this plan through and avoid public involvement. The area cannot support that many housing units. There is not enough suitable land for building that many housing units, there is no room for adequate infrastructure inside or outside of the marked area, and it would eradicate the character and history of the wider local area by essentially concreting over the entire area of map 36 to attain that density.

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68689

Derbyniwyd: 21/04/2016

Ymatebydd: Mr Edward Norris

Cydymffurfio â’r gyfraith? Heb nodi

Cadarn? Heb nodi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

As a resident of Coventry who has lived on the border of Warwick District Council for 40 years I am writing to place on record my objection to the plan to build on the area known as site ref H43 (Kings Hill).
I have listened to all the arguments both "for" and "against" and I can see no justification for building within this area. I request that these plans are reviewed and turned down on the basis that Coventry has more than enough of its own "brown field" sites to accommodate this house building plan.

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68780

Derbyniwyd: 14/04/2016

Ymatebydd: MR ROBERT DONNELLY

Cydymffurfio â’r gyfraith? Heb nodi

Cadarn? Heb nodi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

Objects to allocation: -
- impact on natural environment
- impact on historic environment
- flooding
- additional traffic
- adverse impact on existing facilities and services
- threat to Alvis sports club
- loss of landscape and visual amenity
- should look to other sites and promote regeneration

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68812

Derbyniwyd: 22/04/2016

Ymatebydd: Mrs Ann Bush

Cydymffurfio â’r gyfraith? Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

Not positively prepared - rapid response to inspector's comments on failure to meet Coventry's needs.
Lack of consultation on proposals to use land at Kings Hill.
Too many houses proposed for site - will dwarf Finham.
Significant infrastructure will be required to deliver site - adverse impacts on habitats. No detailed biodiversity study undertaken.
Flooding from Finham Brook.
Potential contamination of drinking water supply.

Atodiadau:

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68849

Derbyniwyd: 21/04/2016

Ymatebydd: Mr. Tony Swann

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

Object to allocation: -
- loss of open space between Coventry and WDC
- flood risk and natural drainage adversely affected
- adverse impact on habitats, wildlife and woodland
- existing traffic congestion will be exacerbated by limited opportunities for access onto new site.

Atodiadau:

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68862

Derbyniwyd: 14/04/2016

Ymatebydd: Mrs Angela Fryer

Cydymffurfio â’r gyfraith? Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

Object to allocation: -
- result of rapid reaction to inspector's concerns, proposing too many houses concentrated in one area - dwarfs Finham
- alternative areas for additional growth
- no previous consideration of site
- loss of open space / green belt unjustified
- lack of / impact on local infrastructure, roads, access, services and facilities
- adverse impact on local habitats and biodiversity
- adverse impact on local environment
- impact on Wainbody Wood
- impact on local drinking water / drainage
- loss of farmland
- adverse impact on sports ground

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68879

Derbyniwyd: 20/04/2016

Ymatebydd: West Midlands Police

Asiant : Tyler-Parkes Partnership

Cydymffurfio â’r gyfraith? Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

To remove land from the Green Belt at Kings Hill and allocate it primarily for: residential development with the potential for some employment land, land for secondary school provision, primary schools, local centre, community facilities, health centre and new rail station would inevitably have an impact on the level of policing which could be provided without commensurate investment in, and provision of, infrastructure to maintain the quality of service expected.
As currently drafted, proposed modified policy DS15 does not make explicit reference to the inevitable impact of the development on the quality and effectiveness of police infrastructure which will arise from the proposed growth and the need for additional police infrastructure.Without
planning polices to require appropriate investment and provision of necessary police infrastructure, the Chief Constable for West Midlands Police believes that the objectives of the NPPF will not be met and for these reasons, Policy DS15 is unsound.

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68918

Derbyniwyd: 14/04/2016

Ymatebydd: Finham Residents Association

Cydymffurfio â’r gyfraith? Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

Object to allocation: -
- should disperse housing in smaller groups
- no suggestion that WDC should take greatest part of Coventry's overspill
- lack of / impact on local infrastructure, services, facilities (including private sports club)
- issues round flooding in area
- poor local road infrastructure and access
- loss of green belt / open land / agricultural land, adverse impacts on character of area
- adverse impacts on Wainbody Wood
- other more suitable areas available
- adverse impact on drinking water / local drainage
- lack of evidence justifying allocation
- impact on historic environment

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68939

Derbyniwyd: 20/04/2016

Ymatebydd: Peter Langley

Cydymffurfio â’r gyfraith? Heb nodi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

Development would be unwarranted projection of the built-up area of Coventry into Green Belt and open countryside It would doubtless be followed soon afterwards by an application for a boundary revision to extend the city's area. Area of good quality landscape making important contribution in separating Coventry from Kenilworth. Relies on a railway station and roads - given the long delay in securing reopening of Kenilworth station, no guarantee that a station at Kings Hill will be open before development takes place

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68976

Derbyniwyd: 21/04/2016

Ymatebydd: Mr. Paul Wood

Cydymffurfio â’r gyfraith? Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

The proposals would mean an equivalent number of houses of twice as many as are already in the Finham area of Coventry. This would need a large increase in the water treatment plant capacity.

Coventry is already densely populated, to propose this many new dwellings concentrated in one area will greatly exacerbate the situation.

There is no allowance for any green belt land between the two housing areas.
It seems a hurriedly prepared plan with no in depth study to its overall effects and with little time for proper public consultation.

Atodiadau:

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68979

Derbyniwyd: 21/04/2016

Ymatebydd: Mrs Chris Hall

Cydymffurfio â’r gyfraith? Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

There seem to be too many houses in one area, twice as many as are already in Finham area of Coventry. There is no allowance for any green space between the two areas.

I am concerned regarding our water supply which comes from the proposed building area and may become contaminated.

The plan will remove a large amount of arable farmland and concentrate and increase the carbon footprint in the area

Atodiadau:

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 68993

Derbyniwyd: 22/04/2016

Ymatebydd: Mr Barry Stelfox

Cydymffurfio â’r gyfraith? Heb nodi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

Loss of ancient woodland and adverse impact on local environment and working farmland
Adverse impact on local and protected habitats
Impact on sports club
Impact on education centres and local schools
Poor accessibility
Increase in traffic and congestion
Issues around water table
no details of proposed railway station
No details of property type or density
No details of social and community facilities and infrastructure
Loss of green belt
What is s106 money to be used for

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 69038

Derbyniwyd: 12/04/2016

Ymatebydd: Baginton Parish Council

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

The plan for 1800 new homes, with a maximum capacity of 4000 homes, is not sustainable from a transport and road infrastructure viewpoint. Amenities for the development listed within the Local Plan, including schools, GP Surgeries, shopping and bus routes are all identified as being north of the proposed site and within Coventry. The existing road infrastructure in Finham and Green Lane are incapable of supporting this development, with little room for any improvements. Similarly, access westward towards Gibbet Hill is not sustainable.
As this development is highlighted as supporting a need within Coventry, daily commutes for workers are also likely to be northwards, or potentially eastwards where sub-regional employment land has been suggested. Insufficient account has been taken of vehicle movement from the site and how this will affect the surrounding area.
Baginton Parish Council acknowledges that some mitigation has been proposed such as New 1, Mod 20, b) on page 19 - 'a new road linking the A46 Stoneleigh junction with Kirby Corner and subsequently to the A452 or A45.' However, such a road would not support commuting northwards or eastwards towards the areas where sub-regional employment growth is suggested. The proposal for new roads recognises and acknowledges that issues exist, but does not adequately address them. It is inconceivable that up to 4000 new homes built to support the growth & development of Coventry does not have the road and transport infrastructure to deliver these residents into the areas where they are needed. The proposal is unsustainable and unsound. Baginton Parish Council OBJECTS

Atodiadau:

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 69230

Derbyniwyd: 22/05/2016

Ymatebydd: Severn Trent Water (Supply Team)

Asiant : GL Hearn

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

Proposed modification to the local plan in its current form is not the most appropriate strategy and, as such, cannot be considered 'sound' having regard to Sections 20(5) of the Planning and Compulsory Purchase Act 2004 and paragraphs 178 - 182 of the NPPF.
Potential for the strategic allocation at King's Hill (H43) currently proposed as a Modification to the Local Plan to help meet such significant employment land needs has not been maximised.

Atodiadau:

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 69296

Derbyniwyd: 22/04/2016

Ymatebydd: Parklands Consortium Ltd

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

Object to proposals:
- contrary to NPPF
- area previously preserved
- proposal to remove site capable of containing 4,000 houses to provide for 1,800 houses unjustified
- no exceptional circumstances demonstrated
- no landscape analysis of whole of SMA that justifies removal of site from green belt

Atodiadau:

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 69365

Derbyniwyd: 15/04/2016

Ymatebydd: Mrs. Jean Parr

Cydymffurfio â’r gyfraith? Heb nodi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

Object to allocation: -
- loss of green belt
- adverse impact on landscape
- adverse impact on wildlife
- adverse impact on ground source water
- area prone to flooding
- adverse impact on heritage, environment, protected trees and hedgerows
- adverse impact of construction phase of site - creates further traffic problems on overcrowded road network

Atodiadau:

Cefnogi

Proposed Modifications January 2016

ID sylw: 69404

Derbyniwyd: 21/04/2016

Ymatebydd: Environment Agency

Crynodeb o'r Gynrychiolaeth:

We have carefully reviewed the modifications proposed within the document based on the Planning Inspectors Interim Report and we find the it meets the tests of soundness:
We agree that the plan is positively prepared, justified, effective and consistent with national policy with the proposed modifications.
We have the following comments to make:
Amendments to Policy DS11 Paragraph 2.4.1
We note that sites were assessed for their suitability against the SFRA Level 1. Warwick District Council's SFRA is dated April 2013 and we recommend that it is updated to take into account changes in Policy (NPPF) and the revised climate
change allowances. The Environment Agency updated their guidance on how climate change could affect flood risk to new developments - 'Flood risk assessments: climate change allowances' published on gov.uk on 19th February and came into immediate effect.
The update is based new scientific evidence. The main changes are to the peak river flow allowances. We are currently preparing new guidance which can be appended to the SFRA before the examination of the Local Plan is resumed.

Atodiadau:

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 69417

Derbyniwyd: 20/04/2016

Ymatebydd: malcolm tattum

Cydymffurfio â’r gyfraith? Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

object: -
- area makes considerable contribution to green belt
- allocation was a rapid response to failings of local plan
- lack of local consultation
- over-concentration of housing and will dwarf Finham and Stoneleigh
- will require additional infrastructure provision
- flood risk
- adverse impact on wildlife and natural environment
- why are offices and railway included on housing shortfall site

Atodiadau:

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 69448

Derbyniwyd: 31/03/2016

Ymatebydd: Councillor John Blundell

Cydymffurfio â’r gyfraith? Heb nodi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

Doubts about figures for housing required
Loss of green belt between Coventry and Kenilworth
Adverse impacts on local road infrastructure and networks
Additional congestion
No provision in Coventry's plan to provide infrastructure outside its boundaries

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 69457

Derbyniwyd: 20/04/2016

Ymatebydd: Mr William Blagburn

Cydymffurfio â’r gyfraith? Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

The loss of large area of green belt is not justified. It includes part of the are of the Finham Brook flood plain.
Understand Coventry's need, but area should be reduced with land south of Kings Hill Lane remaining in the green belt.
Traffic generated could be directed north and south via widened Kings Hill Lane and link to Warwick University Bypass Road which could run form its junction with Gibbet Hill Road across to HS2 and north to Kirby Corner.
City boundary could be enlarged to take in development.
A Stoneleigh village bypass is needed as outlined in emerging Neighbourhood Plan but advised best achieved through the Local Plan.

Atodiadau:

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 69542

Derbyniwyd: 22/04/2016

Ymatebydd: Duncan Gowing

Cydymffurfio â’r gyfraith? Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

Object to allocation: -
- poorly considered response to issues of unsoundness raised by inspector
- can't justify creating high density housing in Kings Hill when other areas are lower density e.g. Nuneaton and Bedworth and could contain higher density development
- loss of green space and impact on / loss of green belt
- flood risk exacerbated from Finham Brook
- adverse impact on drinking water
- lack of capacity at sewage works
- loss of farmland
- poor accessibility to site
- loss of protected trees, hedgerows and habitats
- adverse impact on wildlife, ecology and historic environment

Atodiadau:

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 69573

Derbyniwyd: 18/04/2016

Ymatebydd: Mrs. Jean Dickerson

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

The proposals has been brought forward as a rapid response to the Inspector's initial findings, it has therefore been introduced late in to the process. Rugby and North Warwickshire are less densely populated and could accommodate a greater share of Coventry's overspill. Kings Hill concentrates too many houses in one area and will dwarf neighbouring Finham. The location of the site also removes valuable green space adjacent to the City - green belt has always been protected in the past.

The plan requires considerable infrastructures to address: disturbing bat colonies; flooding; water contamination; drainage issues; archaeology; ancient woodlands, trees and hedgerows; the network of pipes under the site. there has been no in depth ecological study in to the site. Further, Wainbody Wood should be excluded from the site. The proposals will lead to loss of farmland and will increase the carbon footprint. The Alvis sports ground should be protected. Access would need to be from roads that are already congested. Local schools are already at capacity. So where is the infrastructure to support 4000 homes

Atodiadau:

Gwrthwynebu

Proposed Modifications January 2016

ID sylw: 69586

Derbyniwyd: 20/04/2016

Ymatebydd: Mrs Jannice Bateman

Cydymffurfio â’r gyfraith? Nac Ydi

Cadarn? Nac Ydi

Dyletswydd i gydweithredu? Heb nodi

Crynodeb o'r Gynrychiolaeth:

-Plan for 4000 houses is too large.
-Major effect to the environment.
-Infrastructure would not cope up.
-Roads in the area will not cope with the increased traffic.
-There is no benefit to Coventry city.